New Plan Plots a Course for Cross-State Trail Through Central Massachusetts

About one third of the proposed Mass. Central Rail Trail has already been built, but connecting missing links through the hills of Worcester County will be a more challenging project.
New Plan Plots a Course for Cross-State Trail Through Central Massachusetts
The Wayside Trail, part of the Massachusetts Central Rail Trail, passes an abandoned trail station at the Church Street underpass in Weston.

A newly-released feasibility study gives the state a detailed plan for finishing the Massachusetts Central Rail Trail (MCRT), a proposed 104-mile pathway from Northampton to downtown Boston that would largely follow the railbed of the abandoned Massachusetts Central Railroad.

About one third of the trail’s length has already been developed for bike and pedestrian traffic – including the 11-mile Norwottock Rail Trail that extends eastward from downtown Northampton to Belchertown, and a 5-mile segment of the Wayside Rail Trail in Weston (pictured above).

Several other key sections – including an extension of Somerville’s Community Path that’s being built as part of the Green Line Extension project – are in the works.

But connecting the MCRT through the central part of the state, through the hills of Worcester County, will be a more challenging project.

Large segments of the historic rail corridor have been obliterated under suburban sprawl. One crucial segment along the north shore of the Wachussett Reservoir is still an active and busy freight railway.

Even where the corridor is still intact and potentially available for trail development, its condition varies considerably.

In spite of those challenges, about 20 miles’ worth of the MCRT through this region have been built with support and advocacy from Wachusett Greenways, a regional trails organization.

Now, a new study from MassDOT and the Department of Conservation and Recreation (DCR) offers a game plan for connecting the remaining gaps.

The new MCRT Feasibility Study, published earlier this year, conducted a detailed analysis of 68.5 miles’ worth of the former railway between Belchertown and Berlin to take a detailed inventory of the corridor’s condition, evaluate alternative routes through public lands nearby, and recommend future projects that would create a continuous trail through central Massachusetts.

In Holden, where the historic railbed has been lost to development, the plan recommends alternative routes through nearby DCR-owned conservation lands.

And to avoid the active rail line north of the Wachusett Reservoir, the feasibility study recommends routing the MCRT along lightly-used forest roads.

Still unresolved: how to connect the city of Worcester, and its 190,000 residents, to the future MCRT. That connection wouldn’t merely connect the MCRT to the state’s second-biggest city; it would also connect to the Blackstone River Greenway, a partially-built trail that would eventually extend from downtown Worcester to Providence, Rhode Island.

“It is our goal to have the complete East Coast Greenway connecting through Worcester from the Blackstone Greenway to MCRT,” says Kristine Keeney, New England Greenway Coordinator for the East Coast Greenway Alliance.  “The key issue is there’s no identified corridor to make that connection. The completed Blackstone starts in the southern part of Worcester, but there’s nothing in the pipeline to connect it north towards the MCRT.”

Photo of Christian MilNeil
Christian has edited StreetsblogMASS since its founding in spring 2019. Before that, he was a data reporter for the Portland Press Herald in Maine. Got tips? Send them to me via Signal, the encrypted messaging app, at 207-310-0728.

Read More:

Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.

More from Streetsblog Massachusetts

Tuesday’s Headlines Try, Try Again

April 14, 2026

Drivers Killed Two Victims This Weekend, In Boston and Webster

April 13, 2026

Eyes On the Street: Bikes, Pedestrians, and Buses Get More Space In Sullivan Square

April 13, 2026

Monday’s Headlines Show the True Cost of Climate Change

April 13, 2026

Unpublicized City Hall Polling Reveals Broad Support for Bike Projects, Blue Hill Ave. Bus Rapid Transit

April 9, 2026
See all posts