Pandemic Adds to Delays for New Orange and Red Line Cars

A new Orange Line train at Assembly Station in summer 2019. Courtesy of the MBTA.
A new Orange Line train at Assembly Station in summer 2019. Courtesy of the MBTA.

The COVID-19 pandemic is adding to project delays in the MBTA’s effort to replace aging subway cars and alleviate crowding on the Orange and Red lines.

The MTBA celebrated the debut of its first new Orange Line train last August, and a second train entered service in September.

In the eight months since then, though, no new trains have arrived, and the new vehicles that have been running have been pulled from service several times to address mechanical problems.

The new Orange and Red Line cars are a key element in the T’s ambitions to reduce crowding on its two busiest subway lines by putting more trains in service and reducing delays from mechanical problems.

The availability of new trains will take on even greater importance if, as anticipated, the economy begins its phased reopening this summer with increased physical distancing requirements on transit vehicles.

At a January board meeting, MBTA officials reported that the line’s third new trainset could enter service β€œin late February.”

Instead, in early March, at the very beginning of the COVID-19 outbreak, MBTA officials reported that the new trains had been pulled from service again to address ongoing issues with the “bolsters,” which connect the train cars to its wheel assemblies.

The two new trainsets have since re-entered service. Transit advocates have reported sightings of a third new trainset in testing, but those vehicles have yet to open their doors to the public.

The agency has also taken delivery on the first of 252 new Red Line train cars that have been ordered from the same manufacturer: at a press event to show off those new cars in November, T officials said that the first new Red Line trainset could begin rolling this spring.

In response to a press inquiry this morning, MBTA spokesperson Joe Pesaturo wrote in an email that “like almost everything else, the delivery, testing and acceptance processes for new rail cars has been impacted by the pandemic… The MBTA vehicle engineering and operations teams are working closely with the rail car manufacturer to implement measures that allow the procurement process to continue while protecting the health and safety of everyone involved in this complex effort.”

Pesaturo declined to answer a question about whether the manufacturer was still on track to deliver all 140 new Orange Line cars by the end of 2021.

 

ALSO ON STREETSBLOG

Rendering courtesy of the Friends of the Dedham Heritage Rail Trail.

Saturday: Dedham to Hold Delayed Vote on Trail Referendum

|
Voters in Dedham will head to the polls on Saturday to decide whether to support the Dedham Heritage Rail Trail, a 2-mile connection between downtown Dedham, the town’s schools and the Readville commuter rail station. The advisory referendum asks voters whether they “favor, if there is no cost to Dedham taxpayers for design and construction, […]
Arborway project map

DCR Hosts Virtual Meeting to Discuss Arborway Safety Improvements

|
The state Department of Conservation (DCR) hosted a second public meeting Wednesday night for a project that’s expected to create new, protected bike and pedestrian routes along the Arborway in Jamaica Plain. The DCR’s “Arborway Parkways Improvement Project” kicked off last winter, and is aiming to produce detailed designs for a construction project that would […]
Advocates say that these upgrades to the commuter rail network would allow trains to run every 15 to 30 minutes on most lines. Courtesy of TransitMatters.

TransitMatters Issues Detailed Game Plan for Regional Rail Upgrades

|
Advocates from TransitMatters have released a detailed, $2.6 billion strategy for upgrading key commuter rail lines to attain 15-minute, all-day service to Beverly, Providence, and along Boston’s Fairmount Line. Last November, the MBTA’s Fiscal and Management Control Board (FMCB) endorsed an aspirational vision to electrify the MBTA commuter rail network to provide all-day, rapid-transit-style service […]