Skip to Content
Streetsblog Massachusetts home
Streetsblog Massachusetts home
Log In
Protected bike lanes

Reconstruction of High-Crash Melnea Cass Boulevard Delayed to 2020

An architects’ rendering illustrates planned safety improvements for the intersection of Melnea Cass Boulevard and Tremont Street in Roxbury. Courtesy of the City of Boston.

Construction of a long-planned safety project for the Melnea Cass Boulevard in Roxbury has been delayed until 2020, according to MassDOT, and won't be complete until 2024.

Melnea Cass Boulevard, which extends from Columbus Avenue to Massachusetts Avenue in Roxbury, ranks among the city's most dangerous road segments. Its junction with Massachusetts Avenue near Boston Medical Center is one of the most dangerous intersections in the city and has been the site of several fatal crashes in recent years, including one in June.

The city and MassDOT began planning for a complete reconstruction of Melnea Cass in 2011, specifying in outreach materials that the project would seek to create "a pedestrian friendly environment with safe crossings" and include "bus rapid-transit and bicycle accommodation along the corridor."

After years of outreach, planners in late 2018 had agreed on a design that would install protected bicycle lanes, raised crosswalks at intersections, improved bus stops, and landscaped medians.

As of Monday, August 19, a city website for the project still states that the project is "on schedule to begin construction in summer 2019."

But MassDOT, the agency responsible for managing the project's construction, confirmed last Friday that the project would miss that timetable.

"The project is scheduled to be advertised for construction bids this fall," wrote MassDOT spokesperson Patrick Marvin in an email message. "Work related activities would then begin in spring 2020. The full project is expected to be completed by the end of 2024."

Becca Wolfson of the Boston Cyclists Union was disappointed to learn of the delay.

"To residents who are waiting for these lifesaving measures, six months of delay is a long time," said Wolfson in a phone interview on Monday (disclosure: Wolfson also serves on the StreetsblogMASS Board of Directors). "We've seen similar issues on the Commonwealth Avenue project in Boston and the Beacon Street project in Somerville. These big capital projects that the state is overseeing are falling behind, and someone needs to be held accountable."

Stay in touch

Sign up for our free newsletter

More from Streetsblog Massachusetts

Roadblocked: Trump’s ‘Big Beautiful Bill’ Eliminates Most Federal Funding For Allston Highway Realignment

Without a formal project agreement in place, MassDOT will receive only $8 million out of a $335 million "reconnecting communities" grant that the Biden administration had pledged.

July 10, 2025

Another Bus Lane Bites the Dust: Wu Administration Forces Chelsea, Charlestown Transit Riders to Wait In More Traffic

The change comes just weeks before the MBTA rolls out a new bus lane enforcement system, which is expected to improve bus service considerably – at least on the dwindling number of streets where dedicated bus lanes still exist.

July 8, 2025

Balanced For Now – But Beacon Hill Is Putting the T Back On the Edge of Another Fiscal Cliff

The state's final budget gives the T about $80 million less than it had planned to spend in the coming fiscal year to cover its payroll and other transit operating costs.

July 7, 2025

Ambulance Data Reveals That Boston Drivers Are 4 Times More Likely to Run Over Pedestrians From Black Neighborhoods

"Overall, residents of predominantly Black and Latino neighborhoods are about four times more likely than residents of predominantly white neighborhoods to be struck as a pedestrian."

July 1, 2025
See all posts