Quincy Bus Garage Back Out to Bid, Delayed ‘Til End of 2025

A rendering of a new bus garage, showing a gray, low-slung building with eight garage doors facing the viewer, and three black-and-yellow MBTA buses parked in the lot in front. In the foreground, a bike rider and two pedestrians walk along the garage driveway. The MBTA's "T" logo is visible on the top of the building.
A 2021 rendering of the proposed Quincy bus garage on Burgin Parkway in Quincy, across the street from the Quincy Adams Red Line station. Courtesy of the MBTA.

More than 8 months after a ceremonial “groundbreaking” where prominent elected officials planted shovels in a pile of dirt for a photo opportunity, actual construction work on the MBTA’s proposed new bus garage in Quincy – a key infrastructure project in its ambitions to electrify and expand its bus fleet – is still yet to get underway.

Earlier this year, the T had projected a 2024 opening for the new Quincy garage. But this spring, after construction bids came in significantly over the T’s budget, the agency had to pause the project and re-think its approach.

Now, the T has issued a new “request for qualifications” for construction firms that can tweak the project’s design, control costs, and get the new garage open before the end of 2025.

Instead of taking bids on the fully-designed bus garage that the T had conceptualized earlier this year, the T is now seeking bids through a more flexible “construction management at risk” process.

The new approach “allows the MBTA to bring the construction manager on board during pre-construction, and work with the owner and the designer to create more accurate schedules and cost estimates,” MBTA spokesperson Joe Pesaturo told StreetsblogMASS in an email message last week. “The CMAR approach will enable MBTA to work with the contractor and consultants closely to track, monitor, and preserve the overarching project scope and budget that’s aligned with the current market conditions. This delivery method and collaboration will help the authority in meeting the program objectives and goal.”

The T’s projected construction budget for the project remains $280 million, which doesn’t include another $122 million in budgeted “soft costs” related to project design, permitting, site work, and land acquisition.

$280 million is the same price that the T had hoped to spend earlier this year, when construction bids came in as high as $360 million.

Since then, the T has scaled back some non-essential aspects of the new facility’s design in an effort to cut costs.

Among the changes are “the elimination of the (garage’s) third floor, which was unrelated to the bus facility program and intended for other MBTA office needs,” according to Pesaturo.

The T has also been able to get some work done to prepare the site for the future construction project.

In May, workers demolished the abandoned Lowe’s store on the site, and over the summer, the T built a short shared-use pathway along the southern edge of the site to give residential neighborhoods in South Quincy a safer and more direct walking and biking route to the Quincy Adams Red Line station:

A new concrete shared-use path runs alongside fencing with lights towards a busy roadway in the distance. To the right of the path are some trees, and to the left, beyond the fence, is an asphalt parking lot.
The MBTA has built this new shared-use pathway along the southern edge of its new Quincy bus garage site. The path connects Columbia Street in South Quincy to the Quincy Adams Red Line station on Burgin Parkway. Photo courtesy of the MBTA.

The T is building the new Quincy bus garage to replace an existing 90-year-old garage on the other side of the city, and to provide a modest expansion in the T’s garage capacity to support the T’s bus service expansion plans. While the current Quincy garage has room for 86 vehicles, the new facility would store up to 120 buses.

The Quincy garage is also a critical element of the T’s bus electrification plans, since new battery-electric buses will require specialized higher-voltage charging equipment.

The T has set an internal goal to electrify half of its bus fleet with roughly 600 battery-powered buses by 2030. To meet that target, the T will need to finish the new Quincy garage and replace or renovate four other garages, including a new 200-bus facility at the Arborway, in the next 8 years.

 

ALSO ON STREETSBLOG

Extensiones de bordillo/banqueta con vegetación en ambos lados del cruce peatonal localizados en la intersección de Somerville Avenue y Merriam Street a lo largo del camino de bici en la Ciudad de Somerville. Extensiones de bordillo/banquetas hacen la calle más angosta y ayudan a reducir la distancia que la gente tiene que cruzar.

Nuevas Normas de Diseño Para Calles Mas Seguras y Verdes

|
El mes pasado, funcionarios municipales y estatales se juntaron para anunciar las primeros normas de infraestructura verde en Boston, con el fin de aumentar la resiliencia de la ciudad contra el cambio climático por medio de pequeñas instalaciones en las calles. Read the article in English.  En una junta de prensa en Central Square Park […]
A photo illustration of a proposed new shared-use path. A wide, paved path runs through the middle of the image and is lined on both sides by trees and shade. To the left is a wooden guardrail and a two-lane roadway.

DCR Proposes New Trail Connection from Hyde Park to Blue Hills

|
Monday evening, the Department of Conservation and Recreation (DCR) presented conceptual design plans to connect the Neponset River Greenway to the Blue Hills via new and upgraded multi-use paths.  Spanning 8.2 miles, the Neponset River Greenway begins in the Boston neighborhood of Dorchester and runs along the Neponset River through the neighborhoods of Hyde Park, […]