Boston, MassDOT Seek ‘Mega’ Cash to Build Allston/I-90 Project
11:11 AM EDT on May 26, 2022
A rendering of the selected “at grade” design for Interstate 90 and Soldiers Field Road along the Charles River waterfront in Allston, a crucial component of the state’s proposed Allston Multimodal Project. A new bike and pedestrian bridge, pictured at right, would link the Paul Dudley White paths to the Boston University campus, the new West Station, and the Packards Corner neighborhood. Courtesy of MassDOT.
On Tuesday, Mayor Michelle Wu and MassDOT submitted a grant application to Washington in hopes of winning $1.2 billion to build the Allston Multimodal Project, a massive reconfiguration of Interstate 90, Soldiers Field Road, and the Framingham/Worcester railroad line on 90 acres of land along the Charles River waterfront in Allston.
The funding request will compete for the U.S. Department of Transportation's new "Mega Grant" funding, a $5 billion competitive grant program that was created in the 2021 infrastructure law and is intended to help states finance unusually large and complex projects.
That funding would match $754 million in committed funds from local and state sources to finish designing and build the Allston project.
For starters, the grant application promises that the new grid of streets that would create several new city blocks between the MBTA tracks and the riverfront will be built in accordance with the city's and the state's "complete streets" design guidelines, with "extensive bicycle and pedestrian infrastructure."
However, the latest conceptual sketches of the project still show that many of those streets will be unusually wide by Boston's standards, with five or more lanes for motor vehicle traffic.
A detail of the proposed new street grid between I-90 and Cambridge Street from the MassDOT concept plan for the Allston/I-90 Multimodal Project. Courtesy of MassDOT.
A statement from the mayor's office also hints that the city will be looking for significant affordable housing commitments from the private development that's expected to occur on those new city blocks, which are owned by Harvard University.
“By prioritizing access to the riverfront, public transit routes, and added space for affordable housing, we can ensure we’re making the right decisions for future generations of Boston residents and visitors," said Mayor Wu in a press statement.
At that time, MassDOT said that it would submit a "notice of project change" (NPC) to complete the necessary state and federal environmental impact statements before the end of 2021.
That means that the necessary permits to build the project likely won't be ready until 2025. Construction could then begin in the fall of that year, and last 7 years to complete the project by fall 2032.
Bear in mind, however, that this schedule presumes that the federal government puts up the $1.2 billion for the project. If the commonwealth doesn't win that funding and needs to cobble together other funding sources to pay for the work, that could introduce further delays for the project.
Finally, the application also affirms MassDOT's commitment to build a new West Station, which would be a stop on the T's Framingham-Worcester regional rail line with a dedicated busway connection to Packard's Corner and new platforms for a proposed new passenger rail line to Kendall Square.
MassDOT had once considered building West Station as a separate project, which likely would have been delayed for years after the highway project had been built.